Timeline 

Phase I: Identification of Projects
County & Municipal Pre-submittal Meetings Spring 2017 
Public Call for Projects July – Aug 2017
TAC approval of project submittal list June 2017
Projects entered into SPOT Online July – Sept 2017
Phase II: Scoring and Ranking of Projects
TAC considers draft ranking and scoring process December 2017
Scores and draft list of programmed statewide mobility projects released March 2018
Deadline for approval of local input point assignment methodologies March 21, 2018
County TIP Meetings and Public Outreach Meeting March - April, 2018
NWPRPO submits Regional Impact project list to NC DOT April – June 2018
Draft list of programmed regional impact projects released July – August 2018
NWPRPO submits Division Needs project list to NC DOT October 2018
Final P5.0 scores released Nov – Dec 2018